(7) Secure foldout roof panel to foldout end
wall. Also, release six latches (16, fig. 4-3)
securing foldout end wall to foldout roof panel.
(8) Reinstall ECU or ventilation fan in the
(7) Using roof support struts, raise and
--
support roof about two inches for clearance.
as required.)
(9) Level shelter using jacks and procedure of
Support foldout end wall to keep it from
falling when latches are released and hinge
(10) Reconnect tie down cables.
pin is removed.
(11) Reconnect electrical cabling and com-
foldout end wall to swingout walls.
(12) Turn all circuit breakers on circuit
hinge (3) connected between foldout floor panel and
foldout end wall.
(10) Carefully remove foldout end wall from
4-13. Foldout Floor Panels.
the expandable shelter.
a. Removal. To remove the foldout floor panels
b. Installation. To install the foldout end wall
from the expandable shelter, perform the following
on the expandable shelter, perform the following
procedure:
procedure:
(1) Carefully place foldout end wall on ex-
Make certain foldout roof panel is solidly
pandable shelter so that its hinge half aligns with
supported during this operation. Also use
the hinge half on the hinged floor panel.
good judgement in moving these panels
since they are extremely heavy.
Support foldout end wall to keep it from
(1) Perform preliminary procedure of
falling until it is secured to swingout walls
by latches provided.
(2) On side of expandable shelter where
(2) Insert hinge pin (4, fig. 4-3) into hinge (3).
foldout floor panel is about to be removed, fold
(3) Secure foldout end wall to swingout walls
both swingout walls to stowed position using
(4) Install leveling jacks at the two comers of
expandable shelter. Refer to figure 3-4 for in-
(3) Remove foldout end wall in accordance
(5) Using roof support struts, lower foldout
1 through 10.
roof panel until it rests n swingout walls and
(4) Support foldout floor panel and remove
foldout end wall.
hinge pin (1, fig. 4-5) from hinge connected be-
(6) Remove struts from roof, and place them
tween center structure floor panel and foldout floor
in stowed position on side of shelter. Pin struts to
panel.
secure.
4-8