TM 10-5410-229-13&P
2-9. PREPARATION FOR MOVEMENT- Contd
(j)
On the center wall frame assembly (7), loosen the handles (8) on the left hand (11) and right hand
(12) purlins and fold the purlins in towards the center.
(k)
Lay the center frame assembly (7) on its side. Loosen the handles (16) at the center peak joint (8) by
turning them upward. Fold the left hand (11) and right hand (12) purlins, the leg assemblies (1), and
the rafter assemblies (9) in towards the center.
(l)
Place the center wall frame assembly (7) into the frame transport bag.
b.
Packinq Instructions. Pack the disassembled MCPS components into the transport bags as indicated below.
Fabric Transport Bag
Fabric Transport Bag
Roof Cap
- 1 ea
Plain Wall
- 1 ea
Entrance Way Wall
- 1 ea
Window Walls
- 2 ea
Floor
- 1 ea
Rain Gutter
- 1 ea
Plain Wall Liner
- 1 ea
Support Straps
- 10 ea
Entrance/Window Wall Liner
- 3 ea
Frame Transport Bag
Tent Pin Container
End Wall Frame Assembly
- 2 ea
Steel Pins, 12 inch
- 8 ea
Center Wall Frame Assembly - 1 ea
Wood Pins, 24 inch
- 8 ea
Telescopic Poles
- 2 ea
Tent Pin Container
- 1 ea
SECTION IV. OPERATION UNDER UNUSUAL CONDITIONS
2-10.
GENERAL. While it is not possible to prepare for all unusual conditions the MCPS will be exposed to, the
following information should be helpful during unusual climatic conditions or nuclear, biological and chemical
contamination.
a.
Operation in Hiqh Wind:
WARNING
All tent lines and frame feet must always be staked down. Failure to do
so can result in injury to personnel and damage to equipment.
2-52