TM 10-9925-100-12&P
0008 00
CONTAINERIZED CHAPEL
OPERATOR TROUBLESHOOTING PROCEDURES
PROCEDURE 2 COVERS
No heat or air conditioning
INITIAL SETUP:
Equipment Condition
CC set up but not in operation
Maintenance Level
Materials/Parts
Operator
None
ARE ECU OR ASH HEATER UNITS
OPERATING?
START AND OPERATE THE ECU OR ASH
NO
UNITS AS DESCRIBED IN TM 9-4120-398-
14 OR TM9-4520-258-14, RESPECTIVELY.
YES
ARE OPERATING CONTROLS ON THE ECU
OR ASH SET CORRECTLY?
REVIEW OPERATING PROCEDURES FOR ECU
OR ASH AS DESCRIBED IN TM 9-4120-398-14
NO
AND TM 9-4520-258-14, RESPECTIVELY. SET
OPERATING CONTROLS TO START THE FLOW
OF CONDITIONED AIR.
YES
IS CONDITIONED AIR BEING DISTRIBUTED
THROUGH THE PLENUM?
CHECK FOR OBSTRUCTIONS IN THE
NO
PLENUM AND REMOVE AS NECESSARY.
YES
REFER AN ECU OR ASH TO DIRECT
SUPPORT MAINTENANCE IN
ACCORDANCE WITH TM 9-4120-398-14
AND TM 9-4520-258-14 RESPECTIVELY.
END OF WORK PACKAGE
0008 00-3/(4 Blank)