TM 10-7360-208-13&P
2-7.
OPERATING PROCEDURES (CONT).
i.
Heater Tank Assembly.
(1) Load the heater tank assembly (1) with 20 gallons (75.7 liters) of water, approximately 8 inches (203 mm)
deep.
(2) Refer to para 2-7d and prepare and carefully place the M2 burner unit (2) in the burner rack (3) under the
heater tank (1). Do not force.
NOTE
If less than 20 trays are to be heated at one time, more than 20
gallons (75.5 liters) of water will be required to cover the trays.
(3)
While the water is being heated, ready the tray-packs (4) for loading into the heater tank.
(4)
When the water has begun to boil, using the tray-pack lifter (5), load a maximum of 20 tray-packs into
the tank in the following manner:
(a)
The trays are to be arranged on edge in two rows of ten.
2-28