TM 10-7360-208-13&P
2-6. ASSEMBLY AND PREPARATION FOR USE (CONT).
d. Griddle Assemblv (1) and Steam Table Assembly (2). The double burner rack (3) and the double base rack (4)
in the griddle assembly (1) are identical to the racks in the steam table assembly (2). Proceed to assemble the griddle
assembly (1) or the steam table assembly (2).
WARNING
Serious injury could occur if heavy equipment is
moved/lifted without sufficient personnel to do the
job. Use proper physical lifting procedures or use a
suitable lifting device or dolly. Wear safety shoes,
gloves and other suitable protective clothing.
(1) In turn, move the double base rack assembly, the double burner rack assembly, two burner units, and the
griddle, or steam table assembly to the location shown in Figure 2-1.
(2) Place the double burner rack (3) onto the double base rack (4) so that the burner units (5) can be slid into the
rack from the operator's side. The heat guards (8) face the operator.
NOTE
M2 burner units may be already installed if
packaged from previous preparation for movement.
(3) Raise heat guards (8). If not installed, slide M2 burner units (5) into the double burner rack (3).
NOTE
Either surface of the griddle can be installed in the
operating position.
(4) Place the griddle (6) or steam table body (7) onto the double burner rack (3).
2-11