THIS SECTION COVERS:
Before Operation PMCS Checks and Services
INITIAL SETUP:
MBU cooled down and removed from appliance
Maintenance Level
Operator
Table 1. Preventive Maintenance Checks and Services for MBU.
ITEM
NO.
INTERVAL
MAN-
HOUR
ITEM TO BE
CHECKED OR
SERVICED
PROCEDURE
EQUIPMENT
NOT READY/
AVAILABLE IF:
1
Before
MBU
WARNING!
Two Person Lift
The MBU weighs approximately 58 pounds (26.3 kg)
fully fueled. Two persons must carry the MBU when
fully fueled, lifting with legs, not back, to prevent injury.
Inspect frame (1) for damage, such as bent frame
members, cracks, dents or broken welds. Check for
damage to fuel nipple (2) and power connector (3).
Check burner well (4) for debris or accumulated food
waste. Inspect fuel lines (5) for leaks. Check control
panel (6) for damage.
Broken frame
weld, fuel nipple or
power connector
damaged or not
secure. Food
waste or debris in
burner well. Fuel
leak or control
panel damaged.
MBU Before Operation PMCS
1
2
3
4
5
6