TM 10602A-13&P
LIGHTWEIGHT MAINTENANCE ENCLOSURE (LME)
0010 00
PREVENTIVE MAINTENANCE CHECK AND SERVICES (PMCS)
0010 00-4
THIS SECTION COVERS:
PMCS Checks and Services
INITIAL SETUP:
Frame Assembly erected
Maintenance Level
Unit
Table 0010 00-1. Preventive Maintenance Checks and Services for LME - continued.
ITEM
INTERVAL
MAN-
ITEM TO BE
PROCEDURE
EQUIPMENT
NO.
HOUR
CHECKED OR
NOT READY/
SERVICED
AVAILABLE IF:
2
During
Frame
Visually inspect frame components for damage, such
Frame parts bent
Assembly
as bents, cracks, dents. Check for missing parts such
or deformed. Quick
as quick release pins (1), and lanyards (2). Check the
release pins
lower leg assemblies (3) for damage to the feet (4).
missing or broken.
Check for condition of the eave (5) and ridge (6) gusset
Feet on lower leg
plates.
assemblies
broken.