TM 10-5410-284-13&P
TM 10602A-13&P
LIGHTWEIGHT MAINTENANCE ENCLOSURE (LME)
0005 00
OPERATION UNDER USUAL CONDITIONS
0005 00-14
LIFT 3
LIFT 4
Gather personnel on the exterior of the structure, two at each arch assembly as described in lift 1. On
command, lift one side of the structure. Install the lower leg assemblies (1) with any and all personnel
available and lock them in place using the attached quick release pins (2).
Starting at one end, Install the purlins (3) at the base of the lower leg assemblies (1) as shown. Unroll
the intermediate panel fabric (4) onto the ground, and finish lacing the end wall panels (5) to the
intermediate panels (4).
.
Gather personnel at the other side of the structure and repeat the steps as described in lift 3.
Hang the power distribution box (7) onto the mid-height horizontal purlin adjacent to the personnel door
and near the 25 foot cord. Open side strap (8). Slide box to the right until side bracket (9) wraps
around vertical leg of frame. Secure with strap (8). When properly erected, the LME should measure
23' 11 5/16" wide at the base, measured outside of arch assembly to outside of arch assembly.
Complete lacing at the corners of the structure and wrap the interior straps (6) (attached to the
interior of the Intermediate Fabric Section, around the purlins (3), to secure the fabric to the frame.