TM 10-7310-281-13&P
MODERN BURNER UNIT (MBU)
PREVENTIVE MAINTENANCE CHECK AND SERVICES (PMCS)
0010 00
0010 00-9
THIS SECTION COVERS:
After Operation PMCS Checks and Services
INITIAL SETUP:
MBU System shut-down and cooled off
Maintenance Level
Operator
Table 4-1. Preventive Maintenance Checks and Services for MBU - continued.
ITEM
NO.
INTERVAL
MAN-
HOUR
ITEM TO BE
CHECKED OR
SERVICED
PROCEDURE
EQUIPMENT
NOT READY/
AVAILABLE IF:
6
After
MBU and
Battery Pack
WARNING! Hot Surfaces
Let the MBU cool down before performing After
Operation PMCS . This will prevent burn injuries.
WARNING!
Two Person Lift
The Battery Pack and MBU weigh approximately 80
(36.3 kg) and 58 (26.3 kg) pounds respectively. Two
persons must carry each unit, lifting with legs, not
back, to prevent injury.
Inspect the MBU burner well (1) for spilled food waste.
Check the MBU for evidence of fuel leaks (2).
Check Regulator Assembly Air Vent (4), and clean if
necessary. Check Air Vent Assembly Orifice (5), and
clean if necessary.
Check the battery charge (3). Clean equipment
components and re-charge batteries if necessary.
Check cables for any damage, and replace if
necessary.
MBU out of fuel.
Burner Well dirty.
Any fuel leaks in
MBU.
Clogged Fuel
Regulator or Vent
Valve Assembly
Orifice air vents.
Battery charge
less than 40%.
Cables damaged.