1.
Tag and disconnect shelter electrical power.
2. Refer to paragraph 4-7 for removal of panel cover, panelboard, light
switches, circuit breakers.
DISASSEMBLY
1.
Remove insulated connectors (1) from inside circuit breaker box (2),
pull conduit and wires, (3) and (4) away from box. Remove other end of
conduit (4) from box on left side of roof beam.
Slide conduit over
wires and discard.
A new piece of conduit which is 2-inches longer
will be used during installation of new box.
2. Remove four screws (5), lockwashers (6), flat washers (7), and remove
circuit breaker box (2) and spacers (8) from the wall.
CHANGE 2