TM 10-5410-230-13
Section III. OPERATOR MAINTENANCE PROCEDURES
3-3. INSPECTION. Refer to Table 2-1, Operator PMCS for inspection procedures.
3-4. CLEANING. Clean all fabric components with mild soapy water (Appendix E, Item 1) and
brush (Appendix E, Item 2). Let fabric components air dry.
3-5. SEAM SEALING.
This task covers: Repair
NOTE
This procedure applies to all Boot Wall types.
INITIAL SETUP
Materials/Parts:
Brush, varnish (Appendix E, Item 3)
Goggles, chemical splash (Appendix E, Item 7)
K-Cote seam sealer (Appendix E, Item 4)
Latex gloves (Appendix E, Item 5)
Respirator, air filtering (Appendix E, Item 8)
Wiping rags (Appendix E, Item 9)
Equipment Condition:
Area to be sealed must be clean and dry (refer to paragraph 3-4). Boot Wall may be left in service
or removed and laid flat. Refer to paragraphs 2-7, 2-8, or 2-9 for removal procedures.
WARNING
FLAMMABLE. Do not smoke or use seam sealer
near open flame.
HARMFUL FUMES. Use seam sealer in well
ventilated area only. Use personal protective
equipment to prevent inhalation of fumes. Failure to
observe this warning may result in serious injury to
personnel from inhalation of seam sealer fumes.
a.
Brush seam sealer onto seam or area to be sealed. Seam sealer may be applied to inside or
outside of fabric. Ensure to overlap onto serviceable fabric by 1/2 inch.
b.
Allow seam sealer to become dry to touch.
c.
Apply a second coat if desired.
3-5/(3-6 blank)