TM 10-5411-200-14
T.O. 35E4-177-1
4-16. (cont)
2.
Install push bar assembly pins (10) at each of three push bar
assemblies.
3. Connect conduit locknut (29) at roof beam area between left side roof
beam (23) and junction box (3).
4.
Connect conduit locknut (28) at roof beam area between left side roof
beam (23) and top of circuit breaker box (19).
5. Connect conduit locknuts (27) at roof beam area between left side roof
beam (23) and each of three fixed roof area ceiling lights (26).
6. Connect wires from left side roof beam (23) to rear of receptacle (8).
(Refer to paragraph 4-46)
7.
Install receptacle (8) in outlet box (9) and tighten two captive screws
(7).
8. Attach duplex receptacle cover (6) to outlet box (9) with screw (5).