TM 10-5410-221-24
1
Terminal (6, 2 per assy)
4
Sleeving, insulation
7
Wire (AN12)
2
Terminal (3, 1 per assy)
5
Contact, socket (9, 3 per assy)
3
Strap, identification
6
Connector (3, 1 per assy)
Figure 6-11-Continued.
Figure 6-12. Surgical lights receptacle box disassembly.
b. Removal.
6-14.
Water Line Heaters Harness Assembly
(1) Jack up the expandable shelter to gain
a. General.
The water box heater harness
access to the water line tunnel under the shelter and
assembly (6, fig. 6-1) consists of an electrical connector
and 29 electrical leads to provide interconnection
between the water system power harness and the water
(2) Remove clamps used to secure the wiring
harness to the water line tunnel.
.