4-5. UNPACKING - Cont'd.
a. Frame assembly and bag
b. Tent pins and bag
c. Fly assembly
d. Liner assembly (Type II only)
e. Tent body assembly
f. Gear loft
g. Tent cover assembly
4-6. INSPECTING UNPACKED EQUIPMENT. Inspect the unpacked components for damage, completeness,
and application of applicable Modification Work Orders (MWOS) as follows:
a. Damage. Check the equipment for damage incurred during shipment. Report any damage on DD
Form 6, Packaging Improvement Report. Also note damage on DA Form 2404, Equipment Inspection and
Maintenance Worksheet, and initiate corrective maintenance procedures in accordance with Section III of this
chapter.
b. Completeness. Inspect the contents of the shipment against the packing slip to see if any items are
missing (See Appendix D, Components of End Item). Report any discrepancies noted in accordance with
instructions in DA PAM 738-750. The equipment can be placed in service even if accessories or other parts/
assemblies that do not affect proper functioning are missing.
c. Modifications. Check DA PAM 25-30 to see if there are any MWOs applicable to the FSCT
components you are unpacking. If an MWO is listed, check to see if it has been applied to the equipment. The
MWO number will be shown on the case/bag near the equipment nomenclature. If a current MWO is listed in
DA PAM 25-30 but there is no evidence that it has been applied to the equipment you are unpacking, note
discrepancy on DA Form 2404, Equipment Inspection and Maintenance Worksheet.
SECTION IV. UNIT PREVENTIVE MAINTENANCE CHECKS AND SERVICES (PMCS)
4-7. GENERAL. There is no separate Unit PMCS required for the Five Soldier Crew Tent. Refer to Chapter 2
for detailed Operator PMCS procedures.
SECTION V. UNIT TROUBLESHOOTING
4-8. GENERAL. There are no separate Unit troubleshooting procedures for the Five Soldier Crew Tent. Refer
to Chapter 3 for operator troubleshooting procedures.
4-2