TM 10-8340-225-10
2-18.
STRIKING PROCEDURES-CONT.
f.
Collapsing Width of the Frame.
(1)
Pull out the locking pins on the roof members on the left side of the frame and collapse the three
telescoping roof members until they automatically lock into position.
(2)
Repeat the above step for the right side of the frame.
NOTE
You should now have an upside down "U".
g.
Folding the Frame.
(1)
Lay the upside down "U" over on its back.
(2)
Unlock the roof members by sliding the locking collars off the hinges.
(3)
Fold the legs down.
h.
Transport and Packing. Before packing, inspect for rips and tears. Brush off excess dirt and debris and ensure
fabric is dry.
(1)
Fabric Components should be packed in the two fabric transport bags. It does not matter which bag
components are placed. However, to maximize efficiency it is desirable to place the components which are
utilized the most on top. Thus, the items used the least will be packed into the bag first, leaving the utilized
components easily available.
2-31