Roll the intermediate fabric panels (1) toward the ridge (2), disconnecting the becket lacing (3) while
rolling the fabric. When within reach of the ridge, remove the ridge hitch clip pins (4) in the ridge posts
(5).
On command, lift the fabric panels (1) off the ridge posts (2). Stepping carefully through the frame (3),
carry the fabric panels away from the structure. Pack the panels in their proper transport covers (4).
The contents of each cover are clearly marked, both on the inside and outside of the cover. Unplug the
25' power cord (5) from the light string, unwrap it from the frame, and pack it in the power distribution
box (6).
Pack the power distribution box (6) into its foam cushions (7), and then into its transport bag (8).