STEP 9
1. Place the two 60 AMP power cables (1) coiled, on the floor between the large frame bags (2).
2. Place the two 60 AMP pigtails (3) coiled, on top of the 60 AMP power cables (1).
3. Place the tent pin bags (4) and the tent stake bags (5) on the floor in front of the power cables.
4. Place two mallets (6) and two sledge hammers (7) on top of the tent pin bags.
2
1
5
6
2
3
4
7
0005 00-68