Drive 16 inch pins at remaining side and end wall footstops at a slight angle, about 15 degrees from I vertical,
toward the tent, and attach footstops (16) to pins.
n.
Working inside tent, tie jumper lines (17) to side, comer, and eave poles.
o.
Adjust ventilator flap lines (18) and tie them to corner eave poles.
p.
Fasten tie tapes at inside corners of tent around comer eave poles. Tent is now erected.
4-11. Erection of Large General Purpose Tent.
a.
Unpack tent (para. 4-4) then perform preventive maintenance checks and services (table 2-1).
b.
Study the ground plan (figure 4-6) carefully for placement of poles and pins.
Figure 4-6. Ground Plan of Large General Purpose Tent.
c.
Refer to view A, figure 4-7, and position tent flat on ground so that comers are square.
d.
Slide fasteners (1) at all tent comers.
e.
Drive 16 inch pins (2) straight up and down at each comer and attach end wall and sidewall footstops (3) to pins.