TM 10-7310-281-13&P
MODERN BURNER UNIT (MBU)
0029 00
UNIT MAINTENANCE PROCEDURES
0029 00-1/2 blank
INSPECT/REPLACE NYLON CABLE STRAPS
THIS SECTION COVERS:
Inspect/Replace
INITIAL SETUP
MBU shut-down and cool (WP 0005)
Maintenance Level
Materials/Parts
Operator
Tools and Special Tools
Shop Equipment Automotive Maintenance and Repair: Organizational Maintenance,
Common No. 1 (WP 0038, Table 2, Item 2)
Inspect/Replace chassis cable straps. Locate the three chassis mounted cable straps (1,2) on the
bottom surface of the MBU. Take note that there are two sizes. Inspect each strap to ensure that it is not
cracked, cut, or otherwise damaged. Replace the chassis cable straps by removing the cables/hoses
retained by the strap. Remove the nut (3) securing the cable strap to the chassis. Install a new cable
strap in place on the threaded chassis stud and fasten with the nut (3) removed earlier. Reinstall the
hoses/cables inside the cable strap.
Inspect/Replace fuel line hose clamps. Locate the two snap-it hose clamps (4) that secure the hose
and electrical wires to the copper fuel line (5). Inspect each clamp to ensure that it is not cracked, cut, or
otherwise damaged. Replace the fuel line cable clamp by removing the damaged clamp. Slide the
replacement clamp over the fuel line, hose, and wire assembly. Engage the locking mechanism of the
strap so as to retain the hoses and cables securely without squeezing or otherwise deforming them.
Replacing Hose Clamps and Chassis Mounted Cable Straps
END OF WORK PACKAGE
1 (WHC-1500-1)
2 (WHC-1000-1)
3
4
5
NOTE:
Assemblies removed
from MBU frame for
clarity.