TM 10-5411-201-14
T.O. 35E4-178-1
4-7.1 (cont)
ASSEMBLY
1.
Align spacers (8) and circuit breaker box (2) with new inserts and
secure with screws (5), lockwashers (6), and washers (7).
2.
Slide new conduit (P/N 5-4-5061-2) over wires and secure in box on left
side of roof beam.
3.
Insert conduit (3) and (4) into c
insulated connectors (l).
4.
Refer to paragraph 4-7 for install
ircuit breaker box (2) and secure with
ation of circuit breakers, light
switches, wiring, and panel board with cover.
5.
Connect shelter electrical power and remove tags.
6.
Refer to paragraph 4-7 for testing.
CHANGE 2
4-13